A can do a piece of work in 10 days and B can do it in 15 days How many days will they take to finish it working togeth...

Type: MCQ • Marks: 1
A can do a piece of work in 10 days and B can do it in 15 days How many days will they take to finish it working together?
Options
A. 5 days
B. 6 days
C. 8 days
D. 9 days
Paid test series. Purchase the package to see the correct answer and explanation. Purchase Now