An activity lying on the critical path generally has:
Type: MCQ • Marks: 1
An activity lying on the critical path generally has:
Options
A. Maximum float
B. Negative duration
C. Unlimited float
D. Zero total float
Explanation
In the conventional CPM framework, critical activities have zero total float. Delaying such an activity delays the project unless corrective action is taken elsewhere.