Which project-management technique is more explicitly associated with probabilistic activity-time estimates?

Type: MCQ • Marks: 1
Which project-management technique is more explicitly associated with probabilistic activity-time estimates?
Options
A. CPM
B. Line organisation
C. Gantt chart
D. PERT
Explanation
PERT generally uses optimistic, most likely and pessimistic time estimates, whereas classical CPM uses a single deterministic duration.