If an activity has ES = 10, duration = 5 and LF = 15, its total float is:

Type: MCQ • Marks: 1
If an activity has ES = 10, duration = 5 and LF = 15, its total float is:
Options
A. 0
B. 5
C. 10
D. 15
Explanation
EF = 10 + 5 = 15. Therefore, TF = LF − EF = 15 − 15 = 0. The activity is critical.