A project may have:

Type: MCQ • Marks: 1
A project may have:
Options
A. Only one possible path
B. More than one critical path
C. No activities
D. Only one activity
Explanation
Two or more paths can have the same longest duration. Such a project has multiple critical paths, increasing schedule risk.