A dummy activity in an AOA network:

Type: MCQ • Marks: 1
A dummy activity in an AOA network:
Options
A. Consumes substantial resources
B. Represents project expenditure
C. Always represents a critical activity
D. Has zero duration and is used primarily to represent logical dependencies
Explanation
Dummy activities have zero duration and no resource requirement. They help maintain correct precedence relationships.