Which statement about the critical path is most accurate?

Type: MCQ • Marks: 1
Which statement about the critical path is most accurate?
Options
A. It consists of the activities with the highest individual durations
B. It is the longest-duration path through the network
C. It always contains the largest number of activities
D. It represents the cheapest path
Explanation
Criticality depends on the total path duration, not necessarily the number or individual duration of activities.