If two predecessor activities must both finish before an activity can start, the earliest start of the successor is gene...

Type: MCQ • Marks: 1
If two predecessor activities must both finish before an activity can start, the earliest start of the successor is generally:
Options
A. The earliest finish of the predecessor
B. The sum of all predecessor durations
C. The maximum of the predecessors' earliest finish times
D. The minimum of the predecessors' latest finish times
Explanation
The successor cannot start until all required predecessors have finished. Therefore, the latest-finishing predecessor determines its earliest start.
Want to attempt the full test series with a timer and instant score? Purchase the package to unlock the complete test. Purchase Now
UPSC Principal & Vice Principal Management Finance Administration

Practice more

This page is indexed for search so students can find questions directly from Google.

Purchase Full Access View full Test Series Browse Test Series
Login / Register
Chat on WhatsApp Go Back Top