Suppose activity A finishes at day 8 and activity B finishes at day 12, and both are predecessors of activity C The earliest start of C is:
Options
A. Day 8
B. Day 10
C. Day 12
D. Day 20
Explanation
Since both predecessors must finish, C can start only after the later predecessor finishes.