Crashing a project means:

Type: MCQ • Marks: 1
Crashing a project means:
Options
A. Deliberately abandoning activities
B. Reducing project duration by allocating additional resources, usually at additional direct cost
C. Increasing project duration
D. Removing all non-critical activities
Explanation
Crashing is a time-cost trade-off technique. It generally involves increasing direct costs to reduce activity duration.