In a project network, an activity represents:

Type: MCQ • Marks: 1
In a project network, an activity represents:
Options
A. A point in time only
B. A reporting relationship
C. A financial statement
D. A task consuming time and usually resources
Explanation
Activities represent actual work. They normally have duration and may require resources.