It cannot be used for project scheduling

Type: MCQ • Marks: 1
It cannot be used for project scheduling
Options
A. Answer: B. Classical CPM assumes relatively certain activity durations
B. Explanation: CPM is strongest when activity times can be estimated reasonably. High uncertainty may make PERT or other probabilistic approaches more suitable.
C. 39. Which of the following is NOT a primary output of CPM?
D. A. Critical path
Explanation
C. Activity floats