Capital and Revenue Expenditure

The activity becomes automatically critical

Type: MCQ • Marks: 1
The activity becomes automatically critical
Options
A. Answer: B. The activity remains within its total float and may not delay project completion
B. Explanation: A delay within available total float does not necessarily affect project completion.
C. 41. If the same activity in Question 40 is delayed by 8 days, which is the most appropriate conclusion?
D. A. It necessarily remains non-critical
Paid test series. Purchase the package to see the correct answer and explanation. Purchase Now
UPSC Principal & Vice Principal Management Finance Administration

Practice more

This page is indexed for search so students can find questions directly from Google.

Purchase Full Access View full Test Series Browse Test Series
Login / Register
Go Back Top