The activity becomes automatically critical

Type: MCQ • Marks: 1
The activity becomes automatically critical
Options
A. Answer: B. The activity remains within its total float and may not delay project completion
B. Explanation: A delay within available total float does not necessarily affect project completion.
C. 41. If the same activity in Question 40 is delayed by 8 days, which is the most appropriate conclusion?
D. A. It necessarily remains non-critical
Explanation
C. Its duration becomes zero