If 4 workers complete a job in 12 days, how many days would 3 workers take at the same rate?

Type: MCQ • Marks: 1
If 4 workers complete a job in 12 days, how many days would 3 workers take at the same rate?
Options
A. 18
B. 15
C. 17
D. 16