A can complete a job in 12 days and B in 18 days. How long will they take together?

Type: MCQ • Marks: 1
A can complete a job in 12 days and B in 18 days. How long will they take together?
Options
A. 9 days
B. 7.2 days
C. 6 days
D. 8 days
Explanation
Combined rate = 1/12 + 1/18 = 5/36 job/day. Time = 36/5 = 7.2 days.