UP TGT Mathematics Commercial Mathematics Test Series - Part 4

A, B, and C can do a piece of work in 11 days, 20 days, and 55 days respectively. How soon can the work be done if A is...

Type: MCQ • Marks: 1
A, B, and C can do a piece of work in 11 days, 20 days, and 55 days respectively. How soon can the work be done if A is assisted by B and C on alternate days?
Options
A. 1) 7 days
B. 2) 9 days
C. 3) 8 days
D. 4) 10 days
Explanation
Total work = LCM(11, 20, 55) = 220 units. Efficiencies: A = 20, B = 11, C = 4. Day 1 (A+B) = 31 units. Day 2 (A+C) = 24 units. 2-day work = 55 units. Number of 2-day cycles = 220 / 55 = 4. Total days = 4 * 2 = 8 days.
Want to attempt the full test series with a timer and instant score? Purchase the package to unlock the complete test. Purchase Now
UP TGT Mathematics

Practice more

This page is indexed for search so students can find questions directly from Google.

Purchase Full Access View full Test Series Browse Test Series
Login / Register
Chat on WhatsApp Go Back Top